The Future-State Value Stream Map will not tell you whether your design is achievable. It will take any cycle time you type and calculate faithfully from it. If you enter times that no team has ever hit, the tool will produce a clean timeline and a flattering efficiency figure, and it will be wrong in a way that looks correct.
It will not cost anything. There is no field for capital, headcount or licence spend. A future state that needs new equipment and a future state that needs only a rearranged queue look identical on this map. You need a separate business case.
It will not manage the change. The map says nothing about who agrees with it, who will resist it, what training is needed or how long the transition takes. Those questions decide whether the design ever becomes real, and the map is silent on all of them.
It will not validate your data. The header in the sample case says 120 orders per day across one 480 minute shift with 30 minutes of breaks. The tool accepts those figures. It cannot check them against a real demand history. If the demand figure is a guess, every result built on it is a guess with decimal places.
It will not replace the current-state map. Without a measured baseline, a future-state map has nothing to improve on. Draw both. And remember that the case used throughout this guide is fictional sample data, included so you can see the mechanics, not a benchmark to copy.