FMEA will not tell you whether your scores are right. Severity 8 and severity 7 is a judgement made by your team. Change the people and the numbers move. The tool multiplies what you give it. It cannot audit your inputs.
The Risk Priority Number is a blunt instrument. A score of 336 is not four times worse than a score of 84. The scales are ordinal, so the arithmetic is a sorting aid, not a measurement. Treat the ranking as a conversation starter. Do not defend a decision purely because one number beat another by a small margin.
FMEA will not find failure modes you did not think of. It is only as complete as the process map and the people in the room. If nobody mentions a step, that step carries no risk in the analysis, which is not the same as carrying no risk in reality.
The post-action scores are predictions, not results. The residual RPN of 72 for order dispatch is what the team expects after the pilot. It is not evidence that the pilot worked. Evidence comes later, in Control and Sustain, when you measure the live process again.
Finally, FMEA will not do the improvement. It will not implement auto-dispatch or build a kanban. It ranks, it assigns, it forecasts. The work still belongs to the owners named in the rows, and so does the follow-up.