Each row needs four things plus a note. The activity describes the work. The owner names who carries it. The target date commits to a finish. The status says where it stands today. The note holds the evidence or the method.
In the sample plan, row one is Review baseline data and process metrics. Owner is the Green Belt. Target date is 2025-03-01. Status is Completed. The note records Baseline DPMO = 12,500. That single note is what turns a tick box into evidence. Anyone reading the plan knows what the activity produced.
Row two is Conduct value-add / non-value-add analysis. Owner is the Process Analyst, target date 2025-03-05, status In Progress, note Focus on order entry step. Row three is Identify potential root causes (fishbone), owned by the Team, due 2025-03-08, Not Started, with the note Cross-functional workshop.
Rows four to six carry the analytical weight. Validate root causes with data sits with the Black Belt, due 2025-03-15, with the note Use hypothesis testing. Prioritise vital-few root causes sits with the MBB, due 2025-03-20, with the note Pareto + impact matrix. Prepare Analyze tollgate review returns to the Green Belt, due 2025-03-25, with the note Present to sponsor.